Home
Page
Community
Management
Clubs
Art Club
Computer Club
Men's Club
Men's Golf Club
Social Club
Tennis Club
Women's Club
Yiddish Club
Banyan
Banner
Associations
Personals
Cop
Banyan
Springs
Rules &
Regulations
Guide
to Banyan Springs
Reports
and
Meeting Minutes


Mgt.Update
12-17-08
Gen
Mtg 11-19-08
Mgt.Update
12-04-08
Wkshp
Mtg 11-06-08
Mgt.Update
11-06-08
Wkshp
Mtg10-30-08
Mgt
Update 10-30-08
Wkshp
Mtg 10-08-08
Mgt.
Update 10-15-08
Wkshp
Mtg 09-18-08
Mgt
Update 09-18-08
Wkshp
Mtg 08-21-08
Mgt.Update
08-21-08
Wkshp
Mtg 07-24-08
Mgt.
Update 07-24-08


Feedback
| |
MANAGEMENT
UPDATE
THURSDAY, SEPTEMBER 20, 2007
=
= = = = = = = = = = = = = = = = = = =
Earlier this week, the Wood Deck Replacement Project was completed by S.P.M.
Inc. The project which consisted of removal of the old wood and stringers,
installation of 96 concrete support posts under the decking, new pressure
treated stringers and extra support braces.
The decking, rails, posts and skirts are Timbertech Composite material,
which has a 25 year warranty and should provide many years of service.
In addition, S.P.M. added extra posts on the railing of the bridge and
replaced handrails around the elevated Mexican Tile.
While working on the Wood Deck Project, it was discovered that the walls of the
rear outside shower area and a few roof support beams were rotten and in need of
replacement. Since this situation
was an emergency and also tied in with completing the rear deck, the repair was
made immediately. Also, during the
project of resurfacing the pool deck, it was discovered that there was no drain
for the pool shower. Since the wood
deck space was open it was decided to go ahead with installing a drain line, in
order to alleviate standing water on the new pool deck.
The supply lines for the Natural Gas Conversion Project have been installed
within the community by a contractor for Florida Public Utilities. Also during
this period, Boucher’s Gas Company made modifications to convert some of the
Association’s equipment for natural gas usage that is not currently being
used. Boucher’s will return to
modify other appliances during the time that the final connections are being
made. Currently, another contractor
is installing the fixtures and Regulator Station at the front entrance where the
main supply line will connect to the property and is awaiting final D.O.T.
approval to connect to the gas line to the major supply line in the middle of
Boynton Beach Blvd. That approval
could come as early as the end of the week, and if that is indeed the case the
conversion could be complete within the next 2 weeks.
Epic Wireless Corporation’s testing and installation of equipment throughout
the community for the Wireless Network Project has progressed well and is
proceeding on schedule. Within 30
days or less, AT & T will begin installing optic fiber from beyond the rear
gate all the way to the Clubhouse. This
installation will facilitate the delivery of the high speed internet access for
the project. Further testing of the
network and security equipment is forthcoming and we anticipate the entire
system to be fully operational sometime in October.
Today, letters will be sent to all of our residents with subscription
information for wireless internet access.
The planned installation of the lights for Tennis Courts 2 & 3 by Air Ref
Electric Inc. has been delayed until October, due to a manufacturer backlog on
the light poles. Originally
scheduled to be done past week, this delay has caused us to postpone the annual
resurfacing of these same tennis courts until the week of November 5th.
Air Ref will require approximately one week for the light installation so
Courts 2 & 3 may be closed for total of 2 to 3 weeks. The tentative date for
the courts to be closed will be October.
Management has received a bid from Sullivan Electric & Pump for $17,000 to
install Flow Meters at 11 Pumps and 1 Well Station, as a result of new
requirements set forth by the South Florida Water Management District for
renewal of the Association’s water permit.
Because of the high cost of this mandated project, management along with
our irrigation contractor, Mike Farrell are planning to install as many of the
meters in-house in an effort cut the cost considerably.
Management is also working with staff at the District to comply with the
mandate by possibly installing the meters in phases over the next couple of
years. Management will keep the
Board advised on this process.
T.E.M Systems is expecting all of the equipment and the proximity access cards
and key fobs to be in next week. Management
will be meeting with T.E.M. at that time and plans for the distribution of
access cards to all residents should be finalized and announced at the next
P.O.A. Workshop Meeting.
The P.O.A. Attorney, Ed Dicker will be representing the Association in Small
Claims Court, in which an owner, James A. O’Connell, is suing the P.O.A. for
$5000 in damages as a result of a $1000 fine being levied against him by the
Violations Committee in September of 2005.
The preliminary hearing is set for October 4, 2007.
In addition, Mr. O’Connell has filed other related claims against
Lakeside Condominium #1 and Custom Property Management.
Management is in the process of getting information on the cost of upgrading the
Restrooms next to the pool. As soon
as we have the information needed, we will pass it along to the Board as we hope
to include the project as a Special Project in the 2008 Budget.
Respectfully submitted,
Rick Leach, L.C.A.M.
Property Manager
|